January 2025 FIL Implementer Call
<aside> ‼️
The FIL implementer call notes are public, unpublisized security issues shall not be disclosed in this doc.
</aside>
| Team/Area | Section Owner | ⬅️Updates Since Last Meeting | ➡️Upcoming Plans |
|---|---|---|---|
| FilOz | @Orjan Roren | Shipped: |
In progress:
Live on https://dashboard.filspark.com | Start testing retrieval of DDO (non-f05) deals by the end of January. | | FIPs | [email protected] | FIP0098 in Last Call until Feb 6. | | | FF Security | [email protected] | 1. PDP Audit with zellic. 2. Telemetry aggregation for IR alerting. 3. Smart contract and eth support in Antithesis. | Forest, Lotus rpc api correctness testing in Antithesis.
Adversarial testing in Antithesis.
NV25 testing in Antithesis. |
Wearing the “F3 lens”
| Theme | Item | Date |
|---|---|---|
| FYI | Chinese New Year break | January 25, 2025 → February 3, 2025 |
| Estimate | F3 implementation work complete | February 7, 2025 |
| Proposed | FIP Last Call | January 31, 2025 |
| Proposed | Actor code freeze | February 14, 2025 |
| Proposed | Lotus RC for Calibnet | February 18, 2025 |
| Proposed | Calibnet upgrade date | February 25, 2025 |
| Proposed | nv25 mainnet upgrade date | March 13, 2025 |
| Proposed | nv25 F3 passive testing | March 14, 2025 → March 28, 2025 |
| Estimate | F3 Activation | April 2, 2025 |
Potential of “Reduce onboarding gas & align value accrual by removing batch balancer and replacing it with a per-sector fee”
FIP 0098 is in last call and could be picked up